After two earlier rounds of bids for the new fire station #4 on Pinehaven came in over budget, Clinton has turned to the Central Mississippi Planning and Development District to craft a financially innovative plan to construct the station.
Working under an entity called the Central Mississippi Public Improvement Corporation, the City has come up with a lease-purchase plan that will allow the building of the new fire station on Pinehaven and the replica train depot in Olde Towne at the same time.
The CMPIC (Central Mississippi Public Improvement Corporation) is a 501 (c) (3) group, the most common tax-exempt type of nonprofit. “Charitable” is broadly defined as being established for purposes that are religious, educational, charitable, scientific, literary, or testing for public safety.
The CMPIC will work with the City of Clinton under a Certificate of Participation to lease the two sites, engage in the construction and lease the buildings back to the City, which will then make the lease payments.
Currently, the City owns the land on which the fire station is to be situated and leases the site of the proposed train depot replica from Mississippi College under a long-term lease agreement.
According to City Attorney Chelsea Brannon, this innovative way of financing will give the City what it needs for the new fire station.
“We had previously bid it out twice, the second time even cutting out features that were in the initial plans; but the bids still exceeded the budgeted $1.635 million. With this method, we work backwards from the budget and still get everything we wanted for the new fire station to serve Clinton residents on the north side of town.”
After the CMPIC provided a list of three possible contractors, Community Development Director Roy Edwards, City Inspector Robert Touchstone, Clinton Fire Chief Jeff Blackledge and Clinton Fire Marshall Richard Hanks visited sites and toured facilities of each contractor. Their choice for the construction project was Shane Ormon Construction Management/Design, Inc. of Clinton.
Ormon’s group is one of the leading design/build commercial builders in Mississippi. They have completed more than fifty commercial projects throughout the Jackson area, including light industrial, healthcare facilities, distribution centers, office buildings, churches and tenant build-outs. They have been successfully completing projects for the past twelve years. Shane Ormon says he is “delighted and very proud” to have been given the construction contract for both the fire station and the train depot. With only slight modifications to the original plan of the train depot and some site plan changes for the fire station, he is confident that his company can bring both structures in on budget, at a combined $2.1 million, and within an eight–month completion date.
He points to buildings his company has completed previously in Clinton, which include Funtime Pre-School; Clinton YMCA; Clinton Healthcare; Rapid Tire X-Change; and the Mississippi College baseball field entrance.
“The engineering process has already started, and we’ll be ready in the next few weeks to start building,” he said. “We want to give the City quality construction that will last a very long time and be a benefit to all the citizens of Clinton.”
Construction is projected to begin on both projects by early March, with anticipated completion in calendar year 2017. Fire Chief Blackledge is delighted that the sorely needed fire station is back on track to be built in 2017.
“We know what we need, and, since station #2 was done just a few years ago, we learned a lot in that process. We’re going to have two drive-through bays, so that our fire trucks don’t have to back in from off Pinehaven Road. The new pumper truck has been ordered, and we expect delivery by July.”
“We’ll have capacity for nine personnel, three on each shift, with sleeping quarters and a dayroom. We’ll have a ‘safe room’ that can accommodate citizens during bad weather, particularly tornadic activity, for people looking for a safe place to shelter. It’s going to really give us an important fire safety facility on the side of town where most of our schools are, as well as serving residents in subdivisions off Pinehaven, Williamson and Kickapoo.”