Kickapoo Road Bridge Open to Traffic

clinton Mississippi Kickapoo bridge construction

 

 

Clinton, Miss. (June 28, 2021) The Kickapoo Road bridge has been opened to the public. The contractor completed the bridge replacement project on Saturday afternoon and turned the project over to the City.

The City of Clinton appreciates the patience of the residents as the extremely wet May and June delayed completion of the project.



 

Higher than average rainfall during the months of May and June caused delays in the replacement of the roadbed. Due to new flood plain elevations, the bridge was required to be raised an additional fifteen (15”) inches. This necessitated the elevation of the approaches to the bridge fifteen (15”) inches in each direction.

RELATED: Two Bridge Replacement Projects to Begin January 4 in Clinton

Existing asphalt was removed, and new base layers were installed. The higher-than-normal rainfall hindered this process and prevented the proper compaction of soil/aggregate prior to paving of the road.

Completion of the Cynthia Road bridge in Clinton is also nearing completion.

The work on Midway Road bridge near McRaven Road, that was closed on November 19, 2020 following a bridge inspection, will begin this week. This bridge contract was awarded in late May following lengthy approvals of designs by the Mississippi Department of Transportation.

 