City decides to accept 83.7 acres to help settle Hampstead Boulevard debt

By Katherine R. Dougan

Headerman PropertyA deal with the Hederman family to settle a debt owed for the Hampstead Boulevard extension project took a formal step forward on November 2‚ when Clinton’s Board of Aldermen voted 5-1 to negotiate a land swap and cash settlement with the Hederman family.

The debt was incurred when the City paid for the extension of Hampstead Boulevard from Walmart to Morrison Heights Baptist Church. The $3 million Hampstead Boulevard extension project, which cuts through Hederman property, began in November 2014 and was slated for completion in July 2015. However, weather delayed completion until November 2015. Ten years in the planning, the project required permission, involvement and approval from organizations such as the Army Corps of Engineers and MDOT, as well as consideration of flood plain issues. The City built the road, bordered on both sides by Hederman land, and the family agreed to pay for the construction. The Hedermans own land on both sides of Hampstead Boulevard, continuing to the borderline of Butts Park in Jackson.

City Attorney Will Purdie presented the Hedermans’ proposal at the Board meeting. The Hedermans owe $681,396.14 to the City for their share of the Hampstead Boulevard project cost. They propose to settle for $436,396.14 and deed the City 83.7 acres of land south of I-20 for the remainder of the balance owed.

The 83.7 acres has been appraised to be worth between $230,000 and $290,000, and the Hedermans and the City negotiated the land value at $245,000. The northern border of the property is I-20 at the end of the frontage road, and the southern border is Butts Park.

Some of the property (21 acres) is lower-lying land, and 14 acres of the land is swampy. City officials have suggested that acquiring the land gives the City the opportunity for development of the land for use as a regional park, including perhaps walking and bike trails, sports fields, and an RV park around a lake where visitors can come to Clinton for sporting events or can park an RV and stay in Clinton when traveling the Natchez Trace.

Ward 2 Alderman Jim Martin cautioned the Board to gather more information about the property before taking the land swap deal. He voiced opposition to the deal at the Board’s work session as well as in the November 2 Board meeting.

“I’ve got some real problems with this,” said Martin. “I’m not sure we’ve done our due diligence on this one.”

Martin said the Hedermans have been trying to sell that land for a decade, and suggested that the City should seek more information before taking deal for the land.

“We don’t know how many millions of dollars it will cost to put a lake on that property. Is the soil something that would hold a lake, too? There are soils that can’t hold water.” He suggested that the Board look at the feasibility of constructing a lake, the overall cost, and perhaps have some studies done on the land before moving ahead with the land swap deal.
Fisher said he has been talking to the Hedermans about the land since 2015, suggesting that the City might be able to use the land for a regional park.

“The idea of this is intriguing, and the potential for a nice park here sounds good; however, I’ve got some concerns. We’ve looked at this some, and talked about this some, too. This area has some water issues, maybe officially classified as wetlands, and I think that needs to be reviewed and studied some more before we commit to buying this for $245,000 of the City’s money,” Martin said. “I think we need to have these studies done, and some kind of look at it by a consultant before we buy it… we need to do our due diligence before we buy it. If there’s wetlands issues, and we can’t use the property for what we want to do, we need to know that.”

Martin allowed that a 20- to 30-acre lake would be nice, but cautioned it will be expensive. He also recommended soil studies. Martin moved that the motion be tabled before they move ahead. There was no second to the motion, so Martin’s motion died.

Ward 5 Alderwoman Beverly Oliver said she is in favor of the deal, particularly because of the possible addition of an RV park.

“I think it would be a huge asset to our city,” Oliver said. She related to the Board at the work session that a friend of hers who was traveling in an RV wanted to park it in Clinton to stay for a visit.

“I had to send my friend to Timberlake [in Brandon], because we didn’t have anything here.”

Oliver says she particularly likes the idea of RV parking spaces around the lake.

Oliver then made a motion to accept the proposal from the Hedermans that City Attorney Purdie presented to the Board.

“I’d like to feedback off of what Beverly said,” Ward 6 Alderman James Lott III added. “I think this is a great opportunity for the City to use this property for whatever we can. Like the Mayor said, once this deal is done, for a lake, for an RV Park, or if we decide to put some kind of natural item there to appeal to the citizens. I think it is a great idea, and I second the motion.”

“I think Jim’s concerns are legitimate, but because we’re getting this property, it’s kind of a blank canvas of what we can do with it,” Ward 4 Alderman Chip Wilbanks commented. “We can do the studies after we have it, and determine if we can have a lake; maybe it’s smaller than we want, I think we can do that … I think it could be exciting, and I hope we’ll move forward to at least start plans as to the determination of what can be done.”

The Board voted 5-1 to accept the proposal, with Martin dissenting and Ward 3 Alderman William O. Barnett absent.

Marsha Barham, director of the Clinton Visitor Center, says she is a strong proponent of an RV park in Clinton. She is often asked by visitors traveling the Natchez Trace for the location of local restaurants and the nearest RV park. She has to refer them outside of the city, since Clinton does not have an RV park for camping and short stays.

The land swap goes into effect in December; the Hedermans will pay the remaining cash balance on their debt from the Hampstead improvements over five years at 3.5 percent interest, with no penalty for early payoff.