Clinton drainage study in the works

By Randy Bell

Clinton MS Welcome Sign

The City of Clinton will decide if partnering with the U.S. Army Corps of Engineers for a comprehensive study of four local creeks is the best route to take in dealing with local drainage issues, or if the focus should be on individual problem areas.

The Corps would share the cost of the study, and Project Manager Barry Moore says taking a look at the City’s entire drainage system offers some advantages.

“It allows us to determine if one [drainage problem] affects the other, either positively or negatively.”

The City has identified its drainage priorities.

But Moore says, “If we look at it as a whole system, that could change.”

He says they might find that fixing a drainage issue in one area could solve a problem in another part of the City.

Clinton wouldn’t be committed to its share of the funding until an agreement is signed.

“We have to get approval to execute the agreement from our Division Office,” Moore says. “That’s fairly cut and dried.”

It could take up to two years to finish a comprehensive study. The Corps would deliver a report to the City, and decisions would be made on the scope of the construction project, followed by a request for funding. And while there’s always competition from other projects, Moore says it’s a good time to be requesting the money.

“We have some funds that are supposed to be coming down.”

If it’s approved, the actual work could take three to four years—making a total of about six years from start to finish on the entire process.

Moore says, “If all goes well, that’s fairly reasonable.”



 