A project to almost double the capacity of one of Clinton’s wastewater treatment facilities will allow the City to handle the future needs of the Continental Tire plant and continuing residential development in north Clinton. The Board of Aldermen at its July 19 meeting authorized the advertising of bids for improvements at the Lovett plant subject to the plans and specifications receiving approval from the Mississippi Department of Environmental Quality.

 

Lovett is one of four wastewater treatment facilities in Clinton. It serves areas west of Sumner Hill, including both industrial parks, along with neighborhoods north of the Natchez Trace.

 

City Consulting Engineer Greg Gearhart says in order to meet the commitment that was made to Continental and to allow for more homes to built in the Pinehaven Road area, increasing the plant’s capacity was crucial.

 

“It’ll take it from 276,000 to 500,000 gallons a day,” says Gearhart. A typical home produces 250-300 gallons of sewage on a daily basis.

 

As Continental increases production, its wastewater output is projected to eventually reach up to 225,000 gallons a day, which Gearhart says “would more than max out the facility” without an expansion of its capacity. Sewage from sources other than Continental already accounts for 100,000 gallons flowing into the Lovett treatment plant daily.

 

The improvements will also allow more homes to be built and connected to sewer service on the city’s north side.

 

Gearhart says, “We’ll gain the capacity for at least 500 houses.”

 

The aldermen addressed two other sewage issues at the July 19 meeting. They accepted a $155,595 bid from Hemphill Construction Company to finish repairs to a collapsed sewer line along Broadway Street. The problem was discovered back in March, forcing the City to briefly close one of Clinton’s busiest streets, Springridge Road at I-20, to allow crews to replace a portion of the line which runs east from Springridge to Broadway. The work on the final 200-foot segment is not expected to result in any major traffic disruptions. It should be completed within forty-five days.

 

The Board also declared an emergency regarding a sewer problem near the Hunter’s Ridge subdivision in north Clinton. A sewer line leading to a pumping station runs along a creek, but the ground has shifted, and a manhole has moved out of its original position. The Public Works Department and the City Consulting Engineer have been directed to further investigate the problem, prepare a design for the needed improvements and line up a contractor to do the necessary work.