Harper continues to lobby Congress for Clinton funding
By Randy Bell
Gregg Harper knows how things work on Capitol Hill, and the former Mississippi congressman is keeping a close eye on legislation that could get Clinton a step closer to paying for a project which would maintain the viability of the City’s wastewater system while promoting continued development in western Hinds County. Harper has been working for Clinton as a lobbyist, both in Washington and Jackson.
“It’s been a real honor to represent the City of Clinton,” Harper said, prior to an appearance before the Board of Aldermen January 2. “We’ve accomplished a lot thus far. There’s still a lot to be done.”
Harper is trying to secure additional federal funds for the nineteen-mile pipeline to carry treated wastewater from Clinton, Raymond and Bolton to the Big Black River. He told the Board that Congress hadn’t completed work on those funding bills with deadlines quickly approaching.
Harper is hoping that the House and Senate don’t approve a continuing resolution to keep the federal government operating for the rest of the year without approving the funding legislation.
“If we do that, then we’re just sort of out of luck on what would be a significant amount of money that would be there,” he told the Board.
At the same time, Harper noted that his associate, Brett Bailey, has been working on requests to earmark federal funds for Clinton projects for the next fiscal year. And Bailey told the Board the state funding that former House Speaker Philip Gunn was able to get for the Big Black project last year was critical, because that money can serve as a required local match for federal funds.
What it’ll take to complete the pipeline continues to be a moving target. Harper pointed out that the projected price tag now has “an extra digit.” When first proposed, the estimated cost was $97 million, but now it’s around $130 million.
“It would help if the cost didn’t keep going up,” he said, calling inflationary increases for the necessary supplies a “setback.” Still, Harper believes the project is “a very forward-thinking accomplishment.” And, despite challenges the pipeline could face in securing additional money, he remains optimistic.
“I think there’ll be the mood there to continue funding this on the state level and certainly on the federal level, as well.”