More funding on the way for Big Black pipeline

By Randy Bell

Money continues to roll in, bit by bit, to help build a pipeline to carry treated wastewater from Clinton, Raymond and Bolton to the Big Black River for disposal. The $130 million project is aimed at maintaining the viability of Clinton’s sewage treatment system to allow for continued development in the city and to help promote the location of businesses and industries along the pipeline route in western Hinds County.

One of the lobbyists who was hired to represent Clinton on Capitol Hill and at the State Capitol told the Board of Aldermen at its March 5 meeting that action in Washington has paved the way for $7.7 million in additional funding for the project.

“That’s federal money that would go toward the force main along I-20, actually starting at the river and working its way back toward Edwards,” says Brett Bailey, who, along with former Congressman Gregg Harper, lobbies on Clinton’s behalf. According to the Environmental Protection Agency, a force main is a pipeline which conveys wastewater under pressure over an elevation change to a discharge point.

“[That’s] one of the more complicated parts of the project,” Bailey says. The federal funds will be matched with state money the City received last year.

Mayor Phil Fisher says a total of $55 million has been collected or committed to the pipeline.

At the March 5 meeting, the Board voted to accept proposals from a Wiggins company to do an aerial drone survey of the pipeline route. The City will pay Tice Engineering, Inc. $44,500 for the work.

“It’s a helicopter drone with survey equipment on it,” says Consulting City Engineer Greg Gearhart. “It’s got the ability to fly a route, turn around and come back and overlap those shots to pick up a swath of really good detail, about two hundred feet wide.”

The plan was to do the survey before the trees start leafing out.

“They’ll be able to have very precise ground contours, [showing] ditches and the edges of roads,” Gearhart says. “When you’re doing a pipeline like this for a sewer force main, it’s important that you’re able to not only have a plan view of it, but you also have the profile view, so that you can see where the high points of the pipe are going to be, because you have to put in special venting devices at those high points.”