Northside bridge closed pending repairs
By Randy Bell

The bridge between Saddlewood Drive and Twin Lakes North is closed indefinitely for repairs. Traffic is being routed from Northside Drive to Cynthia Road via Magnolia Road North.
A bridge on Northside Drive in Clinton that’s apparently gone years—even decades—without being inspected has been closed because of what the Office of State Aid Road Construction calls “advanced decay” in the bridge’s support structure.
The City has been told that six of the wooden piles and the caps that sit atop the piles need to be replaced. At least one of the piles is severely cracked.
The bridge, located between Saddlewood Drive and Twin Lakes North, is over a branch of Bogue Chitto Creek and was built in the 1970s.
“All crossings on non-state or federal highways designated as bridges are inspected by counties, whether in a municipal limit or not,” says Consulting City Engineer Bill Owen. “An inventory of those bridges is maintained by State Aid, who has the authority to require closure, repair or replacement of those bridges.”
But the one on Northside Drive apparently wasn’t included in that bridge inventory. Owen says after a Clinton Public Works employee reported a washout at the northeastern corner of the bridge, he notified the county, leading to State Aid’s inspection and subsequent letter to Mayor Phil Fisher ordering the closure of the bridge.
Effective March 18, traffic was being detoured via Cynthia Road and Magnolia Road.
As to what happens now, Owen says, “We are working on alternatives but don’t have enough information to give [a] cost estimate or time frame at present.”
Mayor Phil Fisher says it could be late this year or next year before the repairs are completed.
“We’ve told everybody six to nine months to a year,” Fisher says. “A lot of it is going to depend on whether or not we can get a quick response back for what we need to do, get it designed, have an amount of money—and we’re already looking for financial resources we could dip into that might get us there.”
The mayor says, until the scope of the project is determined, it won’t be possible to come up with a price tag.
“How much do you look for? $750,000, $1 million? It just depends on how they design it,” Fisher says.

Pictured is some of the damage to the support structure for the Northside Drive bridge over a branch of Bogue Chitto Creek. Note the cracked pile at the upper left in the photo.
Among the possibilities: replacing the bridge with a double box culvert or upgrading the wooden support structure with new concrete piles and caps, while reusing the existing bridge decks. An important consideration is how the work might impact flood conditions upstream and downstream by affecting water flow under Northside Drive.
Fisher says the City is fortunate the damage was discovered before the bridge collapsed.
“Sometimes, you just have those lucky strokes where somebody, somehow, some way, thought to go look into it, and there it was.”