City looking for funds for Northside bridge
By Randy Bell

The bridge between Saddlewood Drive and Twin Lakes North is closed indefinitely for repairs. Traffic is being routed from Northside Drive to Cynthia Road via Magnolia Road North.
The City of Clinton is hoping State funds will be available to help pay the cost of replacing a bridge on Northside Drive that’s been closed since the middle of March.
The Office of State Aid Road Construction ordered the bridge near the eastern city limits blocked off after an inspection showed “advanced decay” in the wooden support structure. The bridge between Saddlewood Drive and Twin Lakes North was built in the 1970s and apparently had never been inspected before a Clinton Public Works employee reported a problem at the northeastern corner of the bridge.
Consulting City Engineer Bill Owen says it was Hinds County’s responsibility to do the inspections, but the Northside Drive bridge apparently wasn’t included on State Aid’s inventory of bridges.
As drivers continue to detour around the closure, the City is waiting for word on that State money.
Owen says two options are being considered.
“Redo the existing bridge with new [steel] supports and use the existing decks” Owen said. “And the other [option] is to do a totally new bridge.”
He says preliminary plans for replacing the bridge call for using a double 18’ x 10’ box culvert.
“We’ve gone through and looked at how the stream [a tributary of Bogue Chitto Creek] would react with the box culvert,” said Owen. “[It] does nothing to the flood plain. It slightly decreases it, upstream and downstream.”
If the City elects to repair the existing bridge, the new steel piles that would be installed with the decks resting on new concrete caps would prevent the kind of deterioration which prompted the closure.
But Owen has a word of caution: “Part of the issue, as I see it, even though you’re repairing it [with a stronger support structure], you’re still using decks that are fifty years old or better – and we don’t know exactly what the conditions of those are. We can look from the bottom, and they look to be pretty good; but, once you pull them off, there may be spalling [cracks] and things that can’t be seen from the bottom.”
The engineer says repairing the bridge would be slightly less expensive than replacing it, but the City might have a better chance of getting some State funds by building a completely new bridge.
Mayor Phil Fisher said in March that it might be late this year or early next year before the work is completed.