Multi-use path, two bridge projects completed
By Katherine R. Dougan
At the October 19 Board of Aldermen meeting, the Board was able to check the “Final” box on three projects in Clinton.
“I am pleased to ask for permission to finalize the three contracts [on the agenda], the first being for…what we call the [Clinton] Public School District Trail [Multi-Use Path],” Bill Owen, consulting City engineer, told the Board and Mayor. The completed portion of the path runs for approximately 3,000 feet, from Arrow Drive to Crushed Rock Trail, connecting into Traceway Park. The cost came in at $3,026.99 over the estimate because of over-excavating some wet areas and additional material required, Owen explained.
“Quite honestly, I’m really pleased at the way this turned out,” Owen said.
The Traceway Park/Arrow Drive portion of the Clinton Public School District Multi-Use Path project was completed on September 17 for a total cost of $119,085.49. The project contract was implemented on April 23, with a project completion date of August 14. However, inclement weather added a 34-day extension to the project. The Board approved the final payment of $12,352.52 to Thornton Construction.
The rest of the project, which will add the remaining multi-use paths down Arrow Drive to Pinehaven, is currently being completed.
The Board also approved the final quantity change order and final payment of $41,745.44 to Dozer, LLC for the Emergency Road and Bridge Repair project at Cynthia Road.
“This was the project that was originally funded by the ERBR [Emergency Road and Bridge Repair] projects,” Owen said. The project came in under both the budgeted contract as well as the City’s budgeted amount. The contract was awarded June 29, 2020, and completed August 18, 2021, for a total cost of $828,131.26. The original contract bid for this project was $863,019.50.
The final change order and payment was approved for the Kickapoo Emergency Road and Bridge Repair project by the Board. The final payment of $18,660.99 was approved to Fordice Construction. The contract was assigned on November 9, 2020, and, after revisions and changes, was completed July 21, 2021. The total cost for this project was $519,851.22.
“A couple of years ago, everybody was in a major crisis, because bridge inspections weren’t working or hadn’t been [done], and lots of things were going on,” Mayor Phil Fisher commented. The City is now on regular rotation for bridge inspections now, Fisher said.
The only bridge the city has that is a timber-pile construction is the Pinehaven Road Bridge. Timber bridges require a yearly inspection, which means this bridge will be inspected in January or February 2022. The City submitted an Emergency Bridge and Road Repair for this bridge a couple of months ago, Owen said. Concrete pile bridges are inspected every two years. The City has replaced timber piles with concrete piles on bridges as work is needed.
The Midway Emergency Road and Bridge Repair is currently underway. Owen estimates unless there are problems, this project will be completed in November or December 2021.