Estimating what it’ll eventually cost to build a nineteen-mile pipeline to maintain the viability of Clinton’s wastewater treatment system is like aiming at a moving target. The projected price tag more than a year ago was $97 million. And with that number likely rising, the City continues to piece together funding sources to pay for the pipeline to carry treated wastewater to the Big Black River.
A big chunk of the money is coming from the State Capitol. The 2023 Mississippi Legislature approved $20 million for the project. Speaker Philip Gunn pushed for the appropriation, along with Rep. Stephanie Foster, who represents a portion of Clinton.
“We were just so grateful and thankful that this did pass for the City of Clinton,” Foster said after making an appearance at the April 4 Board of Aldermen meeting. Her House District 63 also includes Raymond and Bolton, both of which would benefit from the wastewater project. Last year, the legislature allowed the three municipalities to form a regional authority to pursue funding.
Mayor Phil Fisher said, with the $20 million appropriation, a total of $47 million has been committed to the project—almost halfway to the original goal.
“We’re getting there,” Fisher said. “The good thing is, now we’ve got the doors open, and we’ll keeping moving.”
Much of the money will have to come from the federal government, and a Clinton delegation visited Washington recently to meet with Mississippi’s senators and congressmen, “keeping the project in front of them, getting their advice, their help on where we need to go and what we need to do,” the mayor said. “They’re continuing to work with us. And they’re very enthusiastic about the project themselves.”
The legislature also gave Clinton $8 million for the commercial development that’s in the works near Mississippi College. The money will help pay for the project’s infrastructure.