Pinehaven bridge temporary repair work completed
By Randy Bell
From above, there doesn’t appear to be $83,300 worth of difference in the Pinehaven Road bridge over Bogue Chitto Creek after repairs performed by a Natchez company. But underneath, the work that was done to extend the life of the bridge is evident.
Hope Enterprises, LLC was hired to shore up rotting piles to keep the bridge open until the City can afford to spend $4 million to $5 million to replace it.
Consulting City Engineer Bill Owen says the work involved “splicing” the piles.
“You’re basically taking and cutting off the rotten part, putting a casing around it, filling it up with concrete and putting a new pile in.”
The Board of Aldermen awarded Hope Enterprises the contract at its meeting May 16. The company had thirty days to complete the job beginning June 19, but the work didn’t begin until early July.
“Their crews were working on other projects, and they chose not to start on this project until the project had only a couple of weeks left in the contract time,” Owen says. To make up for lost time and to avoid paying a penalty, the company sent in extra manpower.
“They chose to put three crews to work on it [ten to fifteen people] and get it completed on time,” said Owen.
Owen says the job likely would have taken a crew of three or four some fifteen to twenty days to finish. The expanded crew repaired the bridge in seven days.
Despite the sturdier piles, a three-ton weight limit for the bridge remains posted.