The City of Clinton needs to show that the nineteen-mile pipeline that’s being built to carry treated wastewater to the Big Black River won’t disturb any significant archaeological sites in western Hinds County. An initial survey of the pipeline route has turned up three areas of interest, and the City has agreed to pay an Alabama company an additional $10,000 to further investigate those locations.

“They don’t believe there’s anything really that significant there,” Consulting City Engineer Greg Gearhart told the Board of Aldermen at its March 19 meeting. “We’re not going to find an Indian graveyard or anything like that. But this is just another hoop we have to jump through.”

All Phases Archaeology of Mobile has already been paid $29,000 to dig holes about three feet deep every 100 feet along the route and to sift through the soil that’s removed.

Gearhart told the Board that bits of brick, pottery and glass were found at the three locations and that the Mississippi Department of Archives and History believes the discoveries warrant the follow up survey.

The company will revisit the locations.

“They [will] dig more holes, to see how extensive that site might be,” Gearhart said. “If they dig up some more interesting materials, then they go back, look at old maps, look at old aerial photographs [and] try to see what might have been there, basically trying to determine if there’s a possibility that there was an historic structure of some kind there or anything else.”

If it’s decided there’s something archaeologically significant in the pipeline’s path, Gearhart told the Board that the City would have a couple of options.

“We can either avoid that area, or we can tunnel under it. Tunneling under these three areas would cost in the neighborhood of $200,000,” Gearhart said.

He said he is optimistic that the final results will allow the project to proceed in the most cost-effective way.