Work underway on sewer line repairs

By Randy Bell

Work underway on sewer line repairs

Work underway on sewer line repairs

A Brandon company has begun work to replace two collapsed sewer lines in Clinton, but the construction caused some traffic snarls on one of the city’s busiest streets. One lane of southbound Pinehaven Drive was closed from south of the Natchez Trace to Northside Drive on November 6 so Thornton Construction could dig up the broken concrete pipe and install a new PVC sewer line.

“Unfortunately, these issues rarely occur in convenient locations,” says Public Works Director Phillip Lilley. “Initial attempts were made to clear the blockage in hopes of avoiding this project. If those efforts had been successful, we could have lined the existing pipe without excavation.”

Lilley says there’s more to the project than just digging up the old pipe and putting in the new one.

“The additional time allotted is due to the need for proper soil compaction. We want to ensure the roadway remains free of depressions once Pinehaven is restored. This requires using a compaction device at set intervals during backfill — from the pipe up to the road surface.”

The company has been awarded a $167,765 contract to replace the collapsed pipe on Pinehaven and another one on East College Street. Thornton’s bid came in almost $29,000 below the City’s estimate and was about $3,000 less than the next-lowest bid. The company was given 60 days to complete the work.

Portable sewer bypass pumps have been used at both locations for months. Consulting City Engineer Bill Owen says crews were installing a new 12-inch sewer line on Pinehaven and will be using 8-inch pipe on East College. He says the exact age of the concrete pipe being replaced isn’t known, but it was probably forty to fifty years old.

“Work on College Street will begin shortly after the completion of Pinehaven,” Lilley says. “That portion will take significantly less time, although some traffic obstruction is still expected, since the line runs along the edge of the road.”